Garments gathered at customer site 1
DESCRIPTION Soiled garments gathered at customer and segregated by type of garment in plastic bags. Soiled garments are transported to production facility in plastic bags or garment cages to avoid cross- contamination with other microbial soiled garments. CONTROLS Garment rental customer Phase 2 - Installation AbsorbU GSE Training Proper Personal Protective Equipment (PPE) Designated carts and tubs for soil pick-ups VALIDATION Auditing of routes (Route Manager and Dock Auditor) Scheduled internal HACCP audit Customer onsite audits
POTENTIAL HAZARDS
Physical Hazards Soiled garments
Microbial Hazards Soiled garments Cross contamination from other soiled products
Chemical Hazards None